Topic: 10KV substation power on
• Individual
work scopes and LL internal coordination
O Panel supply vs
installation/assembling
(Argument, interface, cooperation…)
O Fibre cable and control panel (provided
by 2 contractors)
O Maintenance & Insurance
issue
O Missing scope
• Delay
of Panel delivery
• Definition
of “Design issue” – LDI Design vs Design optimization
• Power
panel be enlarged, impact to space management
• Improper
design of cable draw pit, big drop between in and out
• Ventilation design, A/C will be added after
handover